DART RAIL CONSTRUCTION ALERTS
Street location maps are provided courtesy of MapQuest.com. Use the back button in your browser to return to this page.
Level Boarding ConstructionProject Moves to Outlying Rail Stations
Most Work to Take Place on Weekends Over 14 Month Period (June 2009 - August 2010)
• The level boarding project moves to Forest/Jupiter Station on Saturday, Nov. 7 and Sunday, Nov. 8 and to Ledbetter Station on Saturday, Nov. 21 and Sunday, Nov. 22
|
||||||
November 2, 2009
Select a location below to view DART construction activity in that area:Green Line | Orange Line | Blue Line to Rowlett
Green Line Updates:
Downtown Dallas construction information
|
Downtown Dallas: • To support construction around the Bryan/Hawkins intersection: • Motorists will not be able to make left turns from Leonard St. across the DART Rail tracks. View a street location map. |
Market Center Community construction information
|
Market Center Community: • Due to the inclement weather throughout the month of October, Lucas at Harry Hines will be closed through approximately the end of December to complete construction work. View a street location map. |
||
|
Love Field West Community construction information
|
Love Field West Community: Neighborhood Construction Advisory - West of Love Field Construction on DART's exciting Green Line expansion into Northwest Dallas, Farmers Branch and Carrollton has begun in earnest and will continue until passenger service officially begins in December 2010. Listed below is a brief outline of how some of the major streets in the neighborhood west of Love Field will be affected.
• Through approximately the end of November, Denton between Egan and Mockingbird is closed for paving and rail work. One lane is scheduled to reopen at the end of November with work on the road scheduled to be completed at the end of January. View a street location map. • Traffic is reduced to one lane each way at W. Mockingbird Lane and Denton Drive. View a street location map. • There is a traffic switch on Denton Dr. from north of Hawes Ave. to Lovedale for paving work. The northbound lanes are closed and traffic is detoured onto the southbound lanes with one lane open in each direction. Once the northbound lanes are completed, traffic will be switched to the new lanes while southbound lanes are paved. View a street location map. • Through approximately November 16, Hawes Ave. will be closed for road paving and rail installation. View a street location map. Improvements are coming to Little Denton Drive Little Denton Drive will be enhanced to include additional vinyl-coated fencing, added landscaping, curbs and a sidewalk along the street. These improvements will increase safety for the entire neighborhood. The contract for re-construction of Little Denton Drive has been awarded to Phillips/May Construction Company. Construction activity is scheduled to take approximately 10-12 months to complete.View a street location map. • Beginning approximately Monday, November 2, Little Denton will be closed between Empire Central and Lovedale for approximately 3 weeks. View a street location map. • Denton is closed from Shorecrest to Webb Chapel Ext. for underground utility and bridge work until further notice. Detour is available via Harry Hines. View a street location map. |
||
|
Walnut Hill/Denton Area construction information
|
Walnut Hill/Denton Area: Construction for DART's exciting Green Line Expansion Program into Northwest Dallas, Farmers Branch and Carrollton, is underway and will continue until the new passenger service begins in December 2010. Construction in this area will necessitate occasional traffic shifts and detours as some of the local streets and infrastructure are improved. • Webb Chapel Extension at Denton Drive is reduced to one lane in each direction for the installation of underground utilities until further notice. View a street location map. • Denton Drive is closed from Storey Lane to Webb Chapel until further notice. View a street location map. • Denton Drive between Lombardy and Walnut Hill will be closed except for local traffic. Motorists are encouraged to look for local road detour signage. View a street location map. • Century Drive between Doric Street and Denton Drive will permanently close. Local business traffic wishing to access Denton Drive from the east will need to detour along Doric Street to Abernathy Avenue and Lombardy Lane. This work will be followed by subsequent traffic shifts at this location--each lasting for several weeks--to allow for the reconstruction of Century Drive with a direct connection to Abernathy Lane. Road construction on Century Drive is anticipated to continue until Fall 2009. • Walnut Hill near Denton Drive may have daily lane closures. View a street location map. • Work on Walnut Hill at the rail guideway for pavement demolition and street modifications has been postponed. View a street location map. • There is an altered lane configuration on Denton, north of Forest Lane, to accommodate the next phase of paving. View a street location map. • Through approximately mid-November, there will be pavement demolition and replacement work beginning on Royal Lane at the rail guideway. Two lanes of traffic will be maintained in each direction during the project. View a street location map. |
||
|
Farmers Branch Community construction information
|
Farmers Branch Community: Farmers Branch On-Call Boarding With Other DART Routes at Farmers Branch Park & Ride - Effective October 20, 2008 All Farmers Branch On-Call vehicles drop off and board passengers at the temporary transit center on Denton Drive. This is the location currently being used by Bus Routes 44, 185, 204, 247, 331, 400 and 486. Boarding will take place at the sign marked: DEPARTURES All Bus Routes All DART services will use this stop until the new Green Line rail station opens across the street in December 2010. Riders may continue to call 972-880-7786 to schedule an On-Call trip reservation. For other questions about On-Call service, please consult www.DART.org or call 214-979-1111. View a street location map. On Denton at Villa Creek, between I-635 and Farmers Branch Lane, traffic is northbound only for demolition and paving of the southbound lanes. On Villa Creek, traffic is eastbound only. View a street location map. Construction on the Rawhide Creek vehicular bridge has been completed. Southbound Denton Drive between Farmers Branch Lane and Villa Creek remains closed until the work on Villa Creek is completed. Southbound Denton Drive will be detoured west on Valley View, then south on the I-35E service road to Harry Hines. View a street location map.• Various lanes may be closed on Valley View Lane at Denton as signal work is done in the median. View a street location map. • Squire Place at Denton Drive is closed until further notice. View a street location map. • McClintock is closed between Squire Place and Fruitland for utility work until further notice. View a street location map. |
||
|
Carrollton Community construction information
|
Carrollton Community: Construction for DART's exciting Green Line Expansion Program into Northwest Dallas, Farmers Branch and Carrollton, is under way and will continue until the new passenger service begins in December 2010. Construction in this area will necessitate occasional traffic shifts and detours as some of the local streets and infrastructure are improved. • On Valwood Parkway at the rail guideway, there may be lane closures while signal work is done. View a street location map. • Work on Frankford Road at the rail guideway for paving around the median has been postponed. View a street location map. |
||
|
Hatcher Community construction information
|
Hatcher Community: • From Monday, November 2 through Friday, November 6, there may be periodic lane closures on Scyene between 2nd Ave. and Lawnview Ave. View a street location map. • Traffic has been switched to the newly paved lanes on Hatcher at Scyene. One lane in each direction is open. View a street location map. • Left turn lane on Lawnview Avenue at Scyene Road is detoured. Motorists are encouraged to look for detour signage. View a street location map. |
||
|
Lake June Community construction information
|
Lake June Community: • All lanes on Elam Road between Hillburn Drive and Buckner are now open. View a street location map. |
||
|
Orange Line Updates:
Orange Line construction information
|
HARRY HINES/NORTHWEST HWY./I-35/JUSTICE WAY AREA:
Crews will continue bridge construction from just west of Harry Hines/ Northwest Hwy/Spur 482 toward Justice Way requiring various lane restrictions and traffic delays. Motorists are advised to monitor Orange Line Construction alerts to help minimize travel impacts. Please plan your routes, allow extra time to reach your destination, and observe any changes in speed limits or detours. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: Week of November 2: — Nights of November 1 and 5 (9 p.m. to 5 a.m.) - Stemmons Trail at Spur 482, eastbound Spur 482 turnaround onto westbound Storey Lane, and westbound Storey Lane ramp to westbound Spur 482 Week of November 16: — Night of November 15 (9 p.m. to 5 a.m.) - Northbound I-35 , detour information to be provided — Nights of November 16 and 17 (9 p.m. to 5 a.m.) - Southbound I-35 , detour information to be provided — Night of November 17 (9 p.m. to 5 a.m.) - Shoulder and right lane of westbound Spur 482 — Night of November 18 (9 p.m. to 5 a.m.) - Justice Way and the shoulder and right lane of westbound Spur 482 Week of November 9: — Night of November 9 (9 p.m. to 5 a.m.) - Stemmons Trail at Spur 482, eastbound Spur 482 turnaround onto westbound Storey Lane, and westbound Storey Lane ramp to westbound Spur 482 Week of November 16: — Nights of November 18-20 (9 p.m. to 5 a.m.) - Stemmons Trail at Spur 482, eastbound Spur 482 turnaround onto westbound Storey Lane, and westbound Storey Lane ramp to westbound Spur 482 Week of November 30: — Night of November 30 (9 p.m. to 5 a.m.) Stemmons Trail at Spur 482, eastbound Spur 482 turnaround onto westbound Storey Lane, and westbound Storey Lane Ramp to westbound Spur 482 — The week of November 30 (9 p.m. to 5 a.m.) there will be night closures each night on northbound I-35 Week of December 7: — The week of December 7 (9 p.m. to 5 a.m.) there will be night closures each night on southbound I-35 TRINITY RIVER AREA: Bridge construction has moved into the Trinity River area. Motorists can expect to see increased activity in the Trinity as the bridge structure continues to move west. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: SPUR 482/FEDEX/CENTRAL FREIGHT: Crews will continue utility relocation work along the Spur 482 frontage road in front of FedEx and Central Freight. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: SH 114 FRONTAGE ROAD AREA: Expect construction activity and increased truck traffic along the SH 114 frontage road around Loop 12 and the old Texas Stadium. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: TELEPORT BLVD./RIVERSIDE DRIVE AREA: There will continue to be heavy construction activity along Teleport from Riverside Drive through to Las Colinas Blvd. Traffic along Riverside Drive/Teleport Blvd. will continue to be in its current configuration for the next several weeks as crews continue utility relocation work. Teleport Blvd. is closed permanently at SH 114 to through traffic. Access to business drives along Teleport will remain open. Additional lane restrictions in this area may be required for crews to complete activities. Please use caution in this area with changing traffic configurations. Pedestrians need to remember that it is not safe for them to enter construction zones, so they will need to use alternate walking and jogging routes. Motorists are advised to use caution when traveling through this area and obey the advised, posted speed limit of 25 mph. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: LAKE CAROLYN PARKWAY AREA: Construction activity is quickly ramping up in the Lake Carolyn Pkwy. area. Activities will include utility relocations that will require various lane closures and traffic configurations to provide a safe work space for crews to complete construction activities. Pedestrians need to remember that it is not safe for them to enter construction zones, so they will need to use alternate pet walking and jogging routes. Motorists are also asked to monitor construction updates and observe changed speed limits or traffic configurations when traveling through this construction zone. Additional lane restrictions and rolling closures may be required to provide a safe work area as crews continue to progress with the project. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: CONVENTION CENTER AREA: Expect to see increased truck traffic and construction activity around the Convention Center area starting with grading operations. Drill shaft activities are scheduled to begin around mid-November in this area. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: NORTH LAKE COLLEGE/CARPENTER RANCH AREA: Construction activity is scheduled to move into the Carpenter Ranch area around the Meadow Creek/Greenpark Dr intersection starting with utility relocations in early November. Activity will move into the North Lake College area starting with grading during the month of December. Information regarding traffic impacts will be communicated as activities draw closer. ROAD CLOSURES AND LANE RESTRICTIONS: WALNUT HILL/HURD AREA: Construction activity in scheduled to move into the Walnut Hill/Hurd area in November starting with utility relocations. Information regarding traffic impacts will be communicated as activities draw closer. |
Blue Line to Rowlett Updates:
Blue Line construction information
|
• Beginning Monday, October 26, clearing operations will occur in the area north of the rail right of way. This operation will take approximately two weeks. Expect construction equipment to enter the work area from Dexham Road. View a street location map. |
|
||||||

Any time you undertake a construction project, the possibility for danger is elevated. DART is urging everyone to be extra careful around its facilities, vehicles and especially the construction areas. Here are 10 tips you should know.
- Stop, look and listen for DART vehicles.
- Cross the street or track at designated crosswalks only.
- Never walk, ride or play in front of or behind a DART vehicle.
- Children should always exit the bus through the front door.
- Do not walk, ride or play in a construction area.
- Never walk, ride or play on or near railroad tracks.
- Always stand behind the textured warning strips on rail platforms.
- Be careful when driving or turning across train tracks.
- Never try to beat a train through a crossing.
- Remember: Safety begins with you. Talk to your family.

Subscribe to DART Rail Construction Alerts
|



On Denton at Villa Creek, between I-635 and Farmers Branch Lane, traffic is northbound only for demolition and paving of the southbound lanes. On Villa Creek, traffic is eastbound only. 