DART Rail Construction Alerts
Level Boarding ConstructionProject Moves to Outlying Rail Stations
Most Work to Take Place on Weekends Over 14 Month Period (June 2009 - August 2010)
• Level Boarding Project Moves to Spring Valley Station, Saturday, Feb. 20 and Sunday, Feb. 21 and to VA Medical Center Station, Saturday, Mar. 6 and Sunday, Mar. 7.
|
||||||
February 9, 2010
Select a location below to view DART construction activity in that area:Green Line | Orange Line | Blue Line to Rowlett
Green Line Updates:
Downtown Dallas construction information
|
Downtown Dallas: • To support construction around the Bryan/Hawkins intersection: • Motorists will not be able to make left turns from Leonard St. across the DART Rail tracks. View a street location map. |
Market Center Community construction information
|
Market Center Community: • Due to inclement weather, Lucas at Harry Hines will be closed through approximately the end of March to complete construction work. View a street location map. |
||
|
Love Field West Community construction information
|
Love Field West Community: Neighborhood Construction Advisory - West of Love Field Construction on DART's exciting Green Line expansion into Northwest Dallas, Farmers Branch and Carrollton has begun in earnest and will continue until passenger service officially begins in December 2010. Listed below is a brief outline of how some of the major streets in the neighborhood west of Love Field will be affected.
• Traffic is reduced to one lane each way at W. Mockingbird Lane and Denton Drive. View a street location map. • There is a traffic switch on Denton Dr. from north of Hawes Ave. to Lovedale for paving work. The northbound lanes are closed and traffic is detoured onto the southbound lanes with one lane open in each direction. Once the northbound lanes are completed, traffic will be switched to the new lanes while southbound lanes are paved. View a street location map. An Update on Improvements Under Way on Little Denton Drive Construction related to DART's Light Rail Green Line has begun along Little Denton Drive, with a series of enhancements including additional vinyl-coated fencing, added landscaping, curbs and sidewalk upgrades. Upon completion, these improvements will increase safety for the entire neighborhood. View a street location map. Work has been planned in phases, with each street closure affecting one block at a time. Sidewalks will remain open during the road construction portion of the project to maximize access for residents. PHASE 1 - Empire Central to Anson, In Progress PHASE 2 - Bombay to Langdon PHASE 3 - Langdon to Amherst PHASE 4 - Amherst to Burbank • Little Denton between Amherst and Lovers and between Langdon and Gilford is open to local traffic only. Little Denton is open between Empire Central and Lovedale. View a street location map. Notice of Temporary Street Closures - Anson and Little Denton Effective On or After December 21, 2009 Anson at the railroad tracks will be closed for approximately 1 1/2 months beginning on or about December 21. A portion of Little Denton from Anson south will also be closed for approximately two weeks (see map). Traffic will be detoured onto Empire Central. View a street location map (PDF file opens in a new window). • Denton is closed from Shorecrest to Webb Chapel Ext. for underground utility and bridge work until further notice. Detour is available via Harry Hines. View a street location map. |
||
|
Walnut Hill/Denton Area construction information
|
Walnut Hill/Denton Area: Construction for DART's exciting Green Line Expansion Program into Northwest Dallas, Farmers Branch and Carrollton, is underway and will continue until the new passenger service begins in December 2010. Construction in this area will necessitate occasional traffic shifts and detours as some of the local streets and infrastructure are improved. • Webb Chapel Extension at Denton Drive is reduced to one lane in each direction for the installation of underground utilities until further notice. View a street location map. • Denton Drive between Storey Lane and Community Drive has reopened. The portion of Denton between Community Drive and Webb Chapel remains closed until further notice. View a street location map. • Denton Drive between Lombardy and Walnut Hill will be closed except for local traffic. Motorists are encouraged to look for local road detour signage. View a street location map. • Walnut Hill near Denton Drive may have daily lane closures. View a street location map. • Walnut Hill at the rail guideway will have various lanes closed for pavement demolition and street modification work. View a street location map. • There is an altered lane configuration on Denton, north of Forest Lane, to accommodate the next phase of paving. View a street location map. |
||
|
Farmers Branch Community construction information
|
Farmers Branch Community: Farmers Branch On-Call Boarding With Other DART Routes at Farmers Branch Park & Ride - Effective October 20, 2008 All Farmers Branch On-Call vehicles drop off and board passengers at the temporary transit center on Denton Drive. This is the location currently being used by Bus Routes 44, 185, 204, 247, 331, 400 and 486. Boarding will take place at the sign marked: DEPARTURES All Bus Routes All DART services will use this stop until the new Green Line rail station opens across the street in December 2010. Riders may continue to call 972-880-7786 to schedule an On-Call trip reservation. For other questions about On-Call service, please consult www.DART.org or call 214-979-1111. View a street location map. |
||
|
Carrollton Community construction information
|
Carrollton Community: Construction for DART's exciting Green Line Expansion Program into Northwest Dallas, Farmers Branch and Carrollton, is under way and will continue until the new passenger service begins in December 2010. Construction in this area will necessitate occasional traffic shifts and detours as some of the local streets and infrastructure are improved. • One lane is closed in each direction on Belt Line at the rail guideway. View a street location map. • From 11 p.m. on Friday, February 19 to 7 a.m. on Saturday, February 20, Belt Line at the rail guideway will be closed for overhead pedestrian bridge beam placement. View a street location map. • One lane is closed on eastbound Frankford Road at the rail guideway. There will be various lane closures while paving work is done around the median. View a street location map. |
||
|
Hatcher Community construction information
|
Hatcher Community: • Traffic has been switched to the newly paved lanes on Hatcher at Scyene. One lane in each direction is open. View a street location map. • Lawnview Avenue at Scyene Road has been reopened. View a street location map. |
||
|
Lake June Community construction information
|
Lake June Community: From 9 a.m. to 3 p.m. on Tuesday, February 9, Elam at the rail guideway will be closed. From 6 a.m. to 6 p.m. on Tuesday, February 9, Hillburn at the rail guideway will be closed. View a street location map.From 6 a.m. to 6 p.m. on Wednesday, February 10, Jim Miller at the rail guideway will be closed. View a street location map. From 9 p.m. to 5 a.m. on Thursday, February 11, the road to the Keeton Golf Course at the rail guideway will be closed. View a street location map. • All lanes on Elam Road between Hillburn Drive and Buckner are now open. View a street location map. |
||
|
Orange Line Updates:
Orange Line construction information
|
KEY ACTIVITIES HARRY HINES/NORTHWEST HWY./I-35E/JUSTICE WAY AREA: Crews will continue bridge construction from just west of Harry Hines/ Northwest Hwy/Spur 482 toward Justice Way requiring various lane restrictions and traffic delays. Motorists are advised to monitor Orange Line Construction alerts to help minimize travel impacts. Please plan your routes, allow extra time to reach your destination, and observe any changes in speed limits or detours. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: Week of February 8: • February 8, 9 and 10 (8:00 p.m. to 5:00 a.m.) - Westbound Spur 482, all ramps leading to westbound Spur 482, and Stemmons Trail Week of February 8: • February 8 and 9 (9:00 p.m. to 5:00 a.m.) - Ramp from eastbound 482 to eastbound Northwest Hwy TRINITY RIVER AREA: Bridge construction has moved into the Trinity River area. Motorists can expect to see increased activity in the Trinity as the bridge structure continues to move west. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: SPUR 482/FEDEX/CENTRAL FREIGHT: Crews will continue utility relocation work along the Spur 482 frontage road in front of FedEx and Central Freight. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: SH 114 FRONTAGE ROAD AREA: Expect construction activity and increased truck traffic along the SH 114 frontage road around Loop 12 and the old Texas Stadium. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: TELEPORT BLVD./RIVERSIDE DRIVE AREA: Utility relocation activity has started back up along Teleport from Riverside Dr thru to Las Colinas Blvd. Minor lane restrictions may be required for some additional utility relocation work. The majority of the work will be completed at night to minimize traffic impacts. Teleport Blvd will continue be closed permanently at SH 114 to thru traffic. Access to business drives along Teleport will remain open. Please use caution in this area with changing traffic configurations. Pedestrians need to remember that it is not safe for them to enter construction zones, so they will need to use alternate walking and jogging routes. Motorists are advised to use caution when traveling through this area and obey the advised, posted speed limit of 25 mph. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: Pedestrians need to remember that it is not safe for them to enter construction zones, so they will need to use alternate pet walking and jogging routes. Motorists are also asked to monitor construction updates and observe and changed speed limits or traffic configurations when traveling through this construction zone. Motorists are not permitted to enter or park inside construction zones. Additional lane restrictions and rolling closures may be required to provide a safe work area as crews continue to progress with the project. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: CONVENTION CENTER AREA: Expect to see increased truck traffic and construction activity around the Convention Center area starting with grading operations. Drill shaft activities will continue through February in this area. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: NORTH LAKE COLLEGE/CARPENTER RANCH AREA: Construction activity has moved into the Carpenter Ranch area around the Meadow Creek/Green Park Dr intersection and into North Lake College starting with utility relocations. Utility relocation work will continue around the North Lake College near the driveway entrance off MacArthur. Information regarding any traffic impacts will be communicated as activities draw closer. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: WALNUT HILL/HURD AREA: Construction activity will continue in the Walnut Hill/Hurd area in through the month of February. CONSTRUCTION ACTIVITIES: ROAD CLOSURES AND LANE RESTRICTIONS: DFW AREA: Construction activity is moving into the DFW area the month of February. CONSTRUCTION ACTIVITIES: Please note that all dates are tentative as they do not account for weather delays or other schedule impacts. |
Blue Line to Rowlett Updates:
Blue Line construction information
|
• Clearing operations will occur in the area north of the rail right of way. Expect construction equipment to enter the work area from Dexham Road. View a street location map. • Crews will be conducting clearing operations east of the Downtown Garland Station. View a street location map. |
|
|

Any time you undertake a construction project, the possibility for danger is elevated. DART is urging everyone to be extra careful around its facilities, vehicles and especially the construction areas. Here are 10 tips you should know.
- Stop, look and listen for DART vehicles.
- Cross the street or track at designated crosswalks only.
- Never walk, ride or play in front of or behind a DART vehicle.
- Children should always exit the bus through the front door.
- Do not walk, ride or play in a construction area.
- Never walk, ride or play on or near railroad tracks.
- Always stand behind the textured warning strips on rail platforms.
- Be careful when driving or turning across train tracks.
- Never try to beat a train through a crossing.
- Remember: Safety begins with you. Talk to your family.

hideshow















From 9 a.m. to 3 p.m. on Tuesday, February 9, Elam at the rail guideway will be closed. From 6 a.m. to 6 p.m. on Tuesday, February 9, Hillburn at the rail guideway will be closed. 