Skip to Content

DART – Let's Go.

DART Plus. Building a better experience for you.

DART Construction Alerts

Subscribe to:
Silver Line Project Updates Click here to sign-up for email updates   Click here to sign-up for SMS text updates
D2 Updates Click here to sign-up for email updates   Click here to sign-up for SMS text updates
Transit System Plan Updates Click here to sign-up for email updates   Click here to sign-up for SMS text updates
DART Construction Alerts Click here to sign-up for email updates   Click here to sign-up for SMS text updates
DART Community Meeting/Public Hearing Notices Click here to sign-up for email updates   Click here to sign-up for SMS text updates

November 6, 2020

New Hidden Ridge Station Buildout To Require Weekend Orange Line Closures, Effective November 2020


Due to ongoing construction of Irving's new Hidden Ridge Station, DART will temporarily suspend weekend rail service on portions of the Orange Line during November 2020.

Passengers will be able to take shuttle buses between the affected stations and are encouraged to allow extra time. Projected weekend closure dates, including the Friday after Thanksgiving, are as follows, weather permitting:

November 7-8, 14-15, 21-22, 27-28-29: Irving Convention Center Station to North Lake College Station

The shutdowns will enable our contractor Archer Western to install overhead steel canopies at the new station, which is projected to open in late 2021. Weekday service will remain uninterrupted.

Sidewalk Closure Next Phase in Downtown Garland Construction, Effective Monday, October 26, 2020


The third phase in Downtown Garland Station reconstruction begins Monday, October 26, with closing of the sidewalk along Fifth Street between the bus boarding area and rail platforms.

Pedestrians will be directed to a temporary walkway between the two facilities. For passengers with disabilities, a shuttle bus will be provided during the duration of the project. The shuttle will operate between the Red Bus Stop sign (Bay 2) at the transit center and the Walnut Street passenger drop-off area on the north side of the rail station. It will remain in continuous service between 3 a.m. and 1 a.m. daily.

Customers are reminded to use caution in and around construction sites and to obey all warning signs. Thanks for riding DART.

Hidden Ridge Station Construction to Begin in Late April or Early May


Irving residents and Orange Line passengers can expect construction activity between North Lake College and Irving Convention Center stations in late April or early May, as DART's 65th light rail station begins to take shape.

Contractor Archer Western will conduct preliminary excavation work for Hidden Ridge Station on Meadow Creek Drive near Green Park Drive. Trucks, graders, concrete equipment and excavation equipment will be moving in and out of the area during this phase of construction.

Weather permitting, work will be performed weekdays between 7 a.m. and 5 p.m., with occasional weekend activity if needed. All personnel will adhere to strict CDC guidelines to maximize safety during the current COVID-19 emergency.

Possible lane closures and minor interruptions of Orange Line operation are anticipated.

Upon projected completion in early 2021, the facility will accommodate 136 parking spaces and six bus bays.


Silver Line Construction Activity to Begin

Archer Western Herzog (AWH), the design-build contractor for the DART Silver Line Regional Rail Project, will resume field construction activities throughout the Silver Line corridor in June 2020, with overall completion scheduled for March 2023. As specific activities are scheduled along the corridor, additional notifications will be issued to the communities affected.

Construction activity will be conducted within the DART right-of-way. There will be no access to private property, unless coordinated with the property owner(s) in advance. Construction activities will include the following:

  • Daily, temporary and long-term lane closures
  • Set-up for maintenance of traffic control devices
  • Construction surveys
  • Investigation of existing utilities
  • Placement of steel and High-Density Polyethylene (HDPE) casing by open cut and horizontal directional drilling
  • Removal of soil or rock (excavation) for construction of manholes
  • Placement and compaction of layers of earth or rock to form a roadbed (embankment)
  • Installation of conduits and cables within the casing between manholes
  • Splicing, testing and cutover of cables
  • Track removal
  • Clearing sites of all vegetation prior to site work and building construction
Construction will take place during the daytime hours of 7 a.m.-9 p.m. weekdays and 9 a.m.-7 p.m. weekends. This activity will involve heavy construction equipment, including but not limited to loaders, excavators, service vehicles, pickup trucks, small tools, rail saws, speed swings, construction dumpsters, and flat-bed trucks. Other equipment appropriate to the work required may be seen at the various sites. A list of equipment with images can be found at: awhcottonbelt.com/community/construction-equipment.


Construction Alerts History:
» View current alert
» 2020-2021 Construction Alert Updates

» 2019 Construction Alert Updates
» 2016 Construction Alert Updates
» 2015 Construction Alert Updates
» 2014 Construction Alert Updates

Image of a father and child at a rail station

Any time you undertake a construction project, the possibility for danger is elevated. DART is urging everyone to be extra careful around its facilities, vehicles and especially the construction areas. Here are 10 tips you should know.



  1. Stop, look and listen for DART vehicles.
  2. DART Safely logo
  3. Cross the street or track at designated crosswalks only.
  4. Never walk, ride or play in front of or behind a DART vehicle.
  5. Children should always exit the bus through the front door.
  6. Do not walk, ride or play in a construction area.
  7. Never walk, ride or play on or near railroad tracks.
  8. Always stand behind the textured warning strips on rail platforms.
  9. Be careful when driving or turning across train tracks.
  10. Never try to beat a train through a crossing.
  11. Remember: Safety begins with you. Talk to your family.

Back to Top

hideshow